How to calculate remaining landfill life from monthly airspace surveys

Your permit sets a volume limit, not a date. The question every site engineer eventually has to answer for an operator, a board, or a state inspector is simple to ask and hard to get right: how many years of airspace remain in that cell. The math isn't complicated once you have the right inputs. Getting the right inputs, consistently, every month, is the real work.
The arithmetic behind the number
Remaining life comes down to three numbers: the void airspace remaining at your last annual certification, the void airspace consumed since that baseline, and the rate you're consuming it at.
Each monthly survey gives you a topographic surface of the active cell. Subtract that surface from the prior month's and you get a volume of waste placed, in-place airspace consumed, over that period. Do this consistently and you build a fill rate: cubic yards or cubic meters per month.
From there, remaining life in months is:
Remaining void airspace ÷ average monthly fill rate = months to closure
Divide by 12 for years to closure. That's the whole calculation. The division is never the hard part. What's hard is getting clean, comparable numbers into the numerator and denominator month after month.
Why one month of data lies to you
A single month's volume figure moves around for reasons that have nothing to do with your real consumption rate: a wet week that slows compaction, a push to get tonnage in ahead of a tipping fee change, equipment down for maintenance, daily cover placed heavier than usual that period. Any one of those can swing a month's number well off your real trend.
The useful figure is the trailing average, three months, six months, whatever smooths out the operational noise without burying a genuine change in direction. If your fill rate has been climbing across four straight surveys, that's worth flagging before it turns into a surprise at next year's annual report. If it spiked once and came back down, it's probably just noise.
The other thing a single survey can't tell you is settlement. Waste in place compresses over time as organic material breaks down and the column above it consolidates. A cell that appears to have gained a given volume this month often received more than that in fresh placement, with some of the apparent volume actually coming from the existing mass settling underneath. Over a short window this barely matters. Over the full life of a cell it's the difference between a remaining-life estimate that holds up at permit renewal and one that gets questioned.
Turning the trend into a closure date
Once you have a reliable monthly fill rate, the years-to-closure figure is only as good as how current your baseline is. A remaining life estimate built off last year's annual survey and an assumed fill rate is a guess dressed up as a number. One built off this month's surface measured against last month's carries the compaction and settlement that happened in between.
That's the practical case for running the volume calculation monthly instead of annually and extrapolating from there. A fill rate change shows up the quarter it starts, so you can flag it in a working meeting long before it surfaces as a mismatch in next year's annual report.
Landfill Volume is built for exactly this step: a monthly photogrammetric surface of your active cell, measured against the last, so the void airspace and fill rate numbers you need are sitting there waiting instead of something you have to reconstruct from survey crew notes and a spreadsheet three roles old.
If you're still piecing this together by hand each month, it's worth seeing what a consistent monthly dataset against your own cell looks like.